Writing a Project Report 
Peter Coxhead 
 
Projects can be very different: all comments made in these notes must be adapted to your 
particular project. 
If in doubt, consult your project supervisor. 
Read the Project Guidance Notes (start at 
http://www.cs.bham.ac.uk/internal/courses/projects/index.html). This document does not 
replace the Notes. 
Style 
Your report should be written in ‘scientific English’. What this means is not easy to define. Some 
of the suggestions below are taken from Avison (1981). Note that this handout is not in scientific 
style! 
Use a formal rather than a colloquial style 
• Don’t use contractions: for example, write is not rather than isn’t. 
• Don’t use informal words like lots (e.g. replace this caused lots of problems by this caused 
many problems). 
• Don’t use emotive words (e.g. terrible, awful) or slang. 
• Don’t use I unless you are referring to a specific individual choice you made.1 Thus in the 
introduction, if you are explaining why you chose a particular project, then it’s ok to write I 
decided because this was your own individual choice. On the other hand, if you review a 
number of alternative ways of solving a problem and then select the one which you have 
argued is best, I would avoid the use of I, since here you are claiming that anyone, not just 
you, would have made the same choice. So rather than After reviewing the possible design 
choices as discussed above, I decided ..., I would write After reviewing the possible design 
choices as discussed above, it was decided ... In general, expect to use quite a lot of passive 
sentences: the system was constructed rather than I constructed the system. 
Good writing is simple writing 
• Writing in a formal style doesn’t mean that your report should be hard to read because it’s 
full of long words and complicated sentences. Concentrate on getting over the information 
(facts, reasons) to the reader as clearly as possible. 
• Don’t use unnecessary jargon. Keep your intended audience in mind (for the Project Report 
this is a competent computer scientist who is not necessarily a specialist in the area of the 
project). By all means use common technical terms in the field, but avoid unnecessary 
jargon or long words which are just designed to impress. You won’t. 
• Don’t ‘pad out’ your report. Markers won’t be impressed by length. 
• Long and complex sentences should be broken up. The same is true of paragraphs. (On the 
other hand, sequences of very short sentences and paragraphs are irritating.) 
• Spelling, punctuation and grammar should be perfect. Use appropriate tools to check. 
Spelling checkers are normally good (don’t forget to set them to British English). In my 
personal experience, the grammar checker in Microsoft Word is of limited use. Try to get 
someone else to proof read your report: remember that other people are generally better at 
spotting your mistakes than you are. 
                                                
1  Some people say never use I. Check with your project supervisor if in doubt. 
  Page 2 
Plagiarism and Referencing 
Plagiarism is cheating by claiming someone else’s work as your own. Don’t do it! Penalties can 
be very severe: for example, in 2002/03, three Computer Science students failed to get a degree 
because of plagiarism in their projects. Fortunately nothing like that has happened since. 
Accusations of plagiarism in a report can always be avoided by quotation and proper referencing. 
• You cannot copy and paste any text from any source unless it is quoted to make it clear 
that it is copied and not your own words.  
Short quotations should be put in double-quotes like this example: Avison (1981) states 
“Following these rules will ensure that you are not accused of plagiarism.”  
Longer quotations should be made into a referenced ‘block quote’ section: separate 
paragraph(s) indented from both the left and the right. 
• Material which is quoted must be referenced in the text, that is there must be a direct 
indication in the text of its source, using some standard convention (e.g. numbers such as 
[1], or names and dates such as Smith 2001). 
• Material which is paraphrased or otherwise directly used must also be referenced.  
Where you paraphrase ideas or use re-write material in your own words, you must still 
acknowledge the source, e.g. by writing The outline presented here is based on Smith 
(1999). 
• There is a distinction between a list of references at the end of a piece of work and a 
bibliography. The list of references gives full details of the references in the text, whether 
these are numbers or names/dates. The bibliography lists sources you consulted that have 
contributed to the work in a general way, but which are not specifically referenced in the 
text. Usually the list of references should be much longer than the bibliography. 
• For one style of referencing see http://www.cs.bham.ac.uk/~pxc/refs. Use this style unless 
you have agreed the use of a different style with your supervisor. 
• You are not expected to re-invent the wheel; indeed you can legitimately be penalized for 
doing so. It’s good software engineering practice to re-use code. But you must make clear 
which parts of your code are taken from elsewhere and which are original. Carefully 
commenting your code can achieve this. 
You also need to take precautions against other people copying your project, leading to you 
being falsely accused of collusion. If your code and project report are on a networked machine, 
make sure the permissions do not allow viewing. Put your name as author in every Java class. 
Ordering and Content 
Remember that the project report should tell a story. This doesn’t mean telling the reader what 
you did, step by step – we’re not interested in an autobiography. It means making sure that the 
sections of your report follow logically one after the other and add up to something coherent. A 
key to this is making your account linear. YOU know what comes next; the reader doesn’t. 
Time after time I read project reports which I can’t properly understand because the author has 
assumed that I know what comes later. We all know that actual project work is cyclic, iterative, 
even confused. But the report mustn’t be. While it mustn’t falsify what you did, it has to present 
it in a logical order. 
The diagram on Page 4 offers one model for the content of the body of a ‘typical’ project – it is 
not intended to be rigid guide, nor to define numbered chapters or sections. Read the Project 
Guidance Notes as well; some issues discussed there are not covered here. 
• The first component (Introduction) sets broadly what you aimed to achieve and why. The 
final component (Summary/Conclusions) must relate closely to the first. In my view, it 
should be possible to read these two without reading the rest of the report, and know what 
the aims were and how far they were achieved. Don’t be afraid to write a summary which 
repeats what is elsewhere: that’s the point of a summary. 
  Page 3 
• The Background/Review should only review material where the Introduction makes it clear 
why it is included. Don’t put in interesting but marginally relevant background material. The 
reader should always be clear as to why background material is being reviewed. 
• It’s generally useful to have a short component (I’ve called it the ‘Project Specification’) 
which basically says “well, my aims were originally these, but now that I’ve reviewed 
background material, this is more precisely what I’m going to do.” It’s quite acceptable to 
change or refine some of the original aims of the project, but the reasons should be made 
clear. (Note that this component isn’t to do with software: it’s not the requirements 
definition or the software specification. It’s where you show how the original aims of your 
project were refined by your background reading.) 
• Problem Analysis and Solution Design are what we want to read. Implementation details 
should be avoided unless some particularly tricky issue arises. Concentrate on explaining the 
decisions made and the reasons for them. 
• Validation/verification in general and testing in particular are important. Describe your 
testing strategy, not all the details – by all means put details in an appendix. Convince the 
reader that you’ve thoroughly tested/validated/verified all the stages of your work. 
• The Evaluation is very important. What lessons were learnt during the course of the 
project? Evaluate (with hindsight) both the product and the process of its production. 
Review your plan and any deviations from it. Don’t forget to sell your work! Tell the reader 
what was good, what was achieved. Be honest about limitations – these can be suggestions 
for future work. 
After you’ve written each component, ask yourself: 
• Does this follow from what went before? 
• Have I made it clear how it follows from or relates to what came before? 
• Does it assume anything I haven’t yet explained? 
• Does it ‘point forward’ to what comes next? 
Your report isn’t a ‘mystery novel’ where the reader is supposed to look for clues as to what’s 
going on! 
Accreditation 
To be acceptable for BCS and IET accreditation/exemption, your project must conform to their 
requirements. Most of these are also School requirements for all projects. In particular: 
1. The report should demonstrate an appropriate level of professional competence in the 
practical development of a suitable application, tool or similar product. 
2. Projects must give a clear description of the life-cycle stages undertaken (including 
validation and/or verification as required), describing the use of appropriate tools to support 
the development process. 
3. Evaluation of your work is important. This must include not only the outcomes, but also the 
process and what you have learned from undertaking the project. 
A project acceptable to the School (e.g. a theory project) may not be acceptable to the BCS or 
IET. If you want accreditation, pay careful attention to the points above. 
References 
D E Avison (1981) The Project Report: a guide for students (2nd ed.), Computer Centre, The 
University of Aston in Birmingham. 
  Page 4